Question: Using the data set, draw a network diagram ( Fig . 6 . 4 ) and complete a forward and backward pass ( Fig .

Using the data set, draw a network diagram (Fig.6.4) and complete a forward and backward pass (Fig.6.6 and 6.7).
What activities are on the critical path (Fig.6.8)?
What is the project duration?
Step 2: Build the Gantt Chart (Fig.6.11).
Hangar Activity Detail
Task Name Duration cost Predecessors
1 Hangar Permitting 21 days
2 Application 5 days 275
3 Process time 14 days 02
4 Pre-Order building materials 2 days 03
5 Hangar Permitting Complete 0 days 04
6 Hangar Ground Work 44 days
7 Survey property 4 days 505
8 Set elevation 10 days 2007
9 Prepare site for concrete 30 days 7008
10 Construct tarmac and hangar
foundation 31 days
11 Build concrete forms 10 days 7009
12 Install plumbing passing
through concrete (Internal Sewer)3 days 20011
13 Schedule code inspections 1 day 05,12
14 Order concrete 1 day 012
15 Pour concrete 10 days 60012,14
16 Concrete cured 7 days 015
17 Order specialty equipment 2 days
18 Compressors and air systems 1 day 12505
19 Crane and lift equipment 1 day 7505
20 Hangar Groundwork Complete 0 days 016
21 Hangar Assembly 105 days
22 Assemble Frame 40 days 150016,19
23 Install Crane 7 days 30022
24 Assemble outer structure 30 days 30023
25 Install Hangar Door 14 days 30023
26 Install electrical systems 30 days 75022
27 Install low voltage systems 30 days 85022
28 Install plumbing systems 28 days
29 Air systems 24 days 80018,24
30 Water systems 24 days 65018,24
31 External Sewer systems 24 days 100024
32 Connect to outside sources 4 days 550
24,25,26,27,
29,30,31
33 Finish inside areas 15 days 27532
34 Hangar Assembly Complete 0 days 033
35 Open House 1 day 034

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!