Question: Create a Gantt chart to show an implementation plan for the following transformation initiatives, utilizing the initiative costs, value, durations and dependencies as shown: Initiative

Create a Gantt chart to show an implementation plan for the following transformation initiatives, utilizing the initiative costs, value, durations and dependencies as shown:

Initiative
One-Time Cost to Implement
Annual OpEx Reduction
Implementation Duration
Dependencies on Other Initiatives
001
$0.250MM
$0.1MM
3 months
Start early January 2019
002
$0.500MM
$4.0MM
6 months
Only after 001 is complete
003
$0.150MM
$1.0MM
2 months
Only after 001 is complete
004
$1.050MM
$4.0MM
9 months
Can start halfway thru 002
005
$0.300MM
$0.3MM
2 months
Only after 002 and 003
006
$0.400MM
$3.0MM
6 months
Must finish no later than 005

Which initiative has the earliest payback?

What is the total NPV for the program assuming a 5-year NPV and 10% discount rate?

Step by Step Solution

3.42 Rating (158 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To address the question we will go through the following steps Step 1 Developing the Gantt Chart Start with Initiative 001 Starts in January 2019 and ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!