Question: Create a precedence diagram for the project using the table below. Activity Predecessors Duration (Weeks) Full-time Personnel Required A 3 3 B 5 3 C
Create a precedence diagram for the project using the table below.
Activity Predecessors Duration (Weeks) Full-time Personnel Required A 3 3 B 5 3 C A 3 4 D A 2 5 E B 6 5 F 6 5 G E 3 3