Question: Create a Project Schedule using the table below. Please pay attention to these points: Project Start date is 1-Jan-2022 All activities are clearly and properly
Create a Project Schedule using the table below. Please pay attention to these points:
- Project Start date is 1-Jan-2022
- All activities are clearly and properly labeled
- The relationship between the activities is properly represented
- Duration of the activities are accurate
- Critical Path highlighted and it is correct
- Project End date is correct
- Assign Resources
- Set up Milestones
- Schedule baseline is uploaded on Blackboard in both .mpp and .pdf format
| Customized Connecting Software | |||
| Activity | Task | Preceding Activity | Activity Time (Work Weeks) |
| A | Requirement Gathering | No preceding activity | 10 |
| B | Resource Onboarding | A | 5 |
| C | Valve Design | A | 20 |
| D | Valve Development | B | 15 |
| E | Valve Calibration | C | 50 |
| F | Implant Testing | C | 15 |
| G | Battery Pack Testing | D | 35 |
| H | Integration Testing | E, F, G | 15 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock