Question: Create a Project Schedule using the table below. Please pay attention to these points: Project Start date is 1-Jan-2022 All activities are clearly and properly

Create a Project Schedule using the table below. Please pay attention to these points:

  1. Project Start date is 1-Jan-2022
  2. All activities are clearly and properly labeled
  3. The relationship between the activities is properly represented
  4. Duration of the activities are accurate
  5. Critical Path highlighted and it is correct
  6. Project End date is correct
  7. Assign Resources
  8. Set up Milestones
  9. Schedule baseline is uploaded on Blackboard in both .mpp and .pdf format

Customized Connecting Software

Activity

Task

Preceding Activity

Activity Time (Work Weeks)

A

Requirement Gathering

No preceding activity

10

B

Resource Onboarding

A

5

C

Valve Design

A

20

D

Valve Development

B

15

E

Valve Calibration

C

50

F

Implant Testing

C

15

G

Battery Pack Testing

D

35

H

Integration Testing

E, F, G

15

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!