Question: Create a resource loading chart for the project described by this table and then adjust activities by splitting them or delaying them in order to
Create a resource loading chart for the project described by this table and then adjust activities by splitting them or delaying them in order to meet the resource constraints of 8 hours of work per day. Show your new resource loading chart, indicating which activities have been adjusted. What is the change in project completion dates?