Question: Create a resource loading chart using early start times for the project described by this table (time estimated in days). Assume that the maximum amount

  1. Create a resource loading chart using early start times for the project described by this table (time estimated in days). Assume that the maximum amount of resources used per day is 8; which activities are strong candidates for shifting or splitting (i.e., which activities are over the resource limit and need to be leveled or split)? Propose a strategy for resource leveling to resolve resource conflict for this project.
 Create a resource loading chart using early start times for the

2. Draw the resource loading chart below using the provided scale scheme

project described by this table (time estimated in days). Assume that the

\begin{tabular}{|c|c|c|c|c|c|} \hline Activity & Time & Resources & Predecessor & Early Start & Slack \\ \hline A & 14 & 4 & & 0 & 0 \\ \hline B & 2 & 5 & & 0 & 6 \\ \hline C & 4 & 5 & A & 14 & 0 \\ \hline D & 9 & 4 & B & 2 & 6 \\ \hline E & 8 & 5 & C & 18 & 0 \\ \hline F & 2 & 3 & C & 18 & 2 \\ \hline G & 3 & 2 & D & 11 & 6 \\ \hline H & 5 & 4 & F, G & 20 & 2 \\ \hline K & 1 & 3 & E & 26 & 0 \\ \hline L & 13 & 4 & H, K & 27 & 0 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!