Question: Create a task flow diagram for the following tasks and determine the critical path. Task Duration Dependent On: A 2 - B 4 A C

 Create a task flow diagram for the following tasks and determine

the critical path. Task Duration Dependent On: A 2 - B 4

Create a task flow diagram for the following tasks and determine the critical path. Task Duration Dependent On: A 2 - B 4 A C 5 A D 4 B E 2 B F 5 C G 3 D, E