Question: Create an activity schedule and determine the critical path for the following tasks: Task Predecessor Time A 3 B A 4 C B 12 A
Create an activity schedule and determine the critical path for the following tasks:
Task Predecessor Time A 3 B A 4 C B 12 A 6 E C,D 3 F C,D 6 G C,D 7 I E,F 2