Create network diagram of project identifying the critical path. Ensure you identify the critical path duration both
Fantastic news! We've Found the answer you've been seeking!
Question:
Create network diagram of project identifying the critical path. Ensure you identify the critical path duration both in calculation and in illustration, as discussed in class. Ensure you label the tasks, durations etc.
Please make a critical diagram based on the information below.