Question: Create project plan in MS Project 2013 Define tasks -Predecessors Resources Find Critical path Task -> View -> Detailed Gantt Check project duration Check resource

Create project plan in MS Project 2013 DefineCreate project plan in MS Project 2013 Define

Create project plan in MS Project 2013 Define tasks -Predecessors Resources Find Critical path Task -> View -> Detailed Gantt "Check project duration Check resource utilization View -> Resource graph Level resources Resource -> Level resource Check project duration Project Data Task Duration Start Resource units Predecessors 1 2 1 2 2 6 3 2 1 3 4 3 2 1 4 2 3 1 1 5 2 7 1 3 6 4 7 1 3 7 2 11 1 2, 4, 5, 6