Question: create the network diagram and determine project duration, critical path, and slack time. 3, begin{tabular}{llc} Activity & Predecessor(s) & Duralion hline A. & &

create the network diagram and determine projectcreate the network diagram and determine project duration, critical path, and slack time.

3, \begin{tabular}{llc} Activity & Predecessor(s) & Duralion \\ \hline A. & & 3 \\ B & A & 4 \\ C & A & 6 \\ D & B & 6 \\ E & B & 4 \\ F & C & 4 \\ G & D & 6 \\ H & E. F & 8 \\ \hline \end{tabular}