Question: Crista is a project manager for large project. She uses EVM on a regular basis. When calculating EVM Crista noticed that the cumulative planned value

Crista is a project manager for large project. She uses EVM on a regular basis. When calculating EVM Crista noticed that the cumulative planned value is 150% higher than cumulative earned value. What does this mean?
Question 7 options:
SPI is 1, ahead of time
SPI is >1 so project is doing well