Question: Crista is a project manager for large project. She uses EVM on a regular basis. When calculating EVM Crista noticed that the cumulative planned value

Crista is a project manager for large project. She uses EVM on a regular basis. When calculating EVM Crista noticed
that the cumulative planned value is 150% higher than cumulative earned value. What does this mean?
00
SPI is 1 so project is doing well
SPI is <1, so it is on schedule
SPI is >1, ahead of time