Question: Critical Path - Complete table and draw per showing critical path Task Time Immediate Predecessors Early Finish Late Finish Slack Critical Path? 1 A 2

Critical Path - Complete table and draw per showing critical path

Task

Time

Immediate Predecessors

Early

Finish

Late

Finish

Slack

Critical

Path?

1

A

2

--

2

B

3

A

3

C

3

B

4

D

7

B

5

E

6

B

6

F

1

C, D

7

G

5

D, E

8

H

4

F, G

9

I

8

G

10

K

2

H, I

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer