Question: Critical Path - Complete table and draw per showing critical path Task Time Immediate Predecessors Early Finish Late Finish Slack Critical Path? 1 A 2
Critical Path - Complete table and draw per showing critical path
|
|
Task |
Time | Immediate Predecessors | Early Finish | Late Finish |
Slack | Critical Path? |
| 1 | A | 2 | -- |
|
|
|
|
| 2 | B | 3 | A |
|
|
|
|
| 3 | C | 3 | B |
|
|
|
|
| 4 | D | 7 | B |
|
|
|
|
| 5 | E | 6 | B |
|
|
|
|
| 6 | F | 1 | C, D |
|
|
|
|
| 7 | G | 5 | D, E |
|
|
|
|
| 8 | H | 4 | F, G |
|
|
|
|
| 9 | I | 8 | G |
|
|
|
|
| 10 | K | 2 | H, I |
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
