Question: Q 2 : A project has been defined to contain the following list of activities and their required completion times. begin { tabular }

Q2: A project has been defined to contain the following list of activities and their required completion times.
\begin{tabular}{|l|l|l|l|}
\hline \begin{tabular}{l}
Activity \\
No.
\end{tabular} & Immediate Activity & \begin{tabular}{l}
Time \\
(weeks)
\end{tabular} & Predecessors \\
\hline 1 & Collect requirements & 3 & \\
\hline 2 & Analyze processes & 2 & 1\\
\hline 3 & Analyze data & 2 & 2\\
\hline 4 & Design processes & 6 & 2\\
\hline 5 & Design data & 3 & 3\\
\hline 6 & Design screens & 2 & 3,4\\
\hline 7 & Design reports & 4 & 4,5\\
\hline 8 & Program & 5 & 6,7\\
\hline 9 & Test and document & 2 & 7\\
\hline 10 & Install & 8,9\\
\hline
\end{tabular}
Q2-A: Draw an Activity Summary Table (including activity, time, immediate predecessors, early finish, late finish, slack, and critical path columns) for the project described above (7 points).
Q2-B: Draw a network diagram using task box format for the activities (4 points)(please note, you can make up each activity's start and end date).
Q2-C: Calculate the earliest expected completion time (3 points).
Q 2 : A project has been defined to contain the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!