Question: Critical Path for Blue Lagoon Pools. The following table lists the activity time estimates (in days) for Blue Lagoon's swimming pool installation project in Problem
Critical Path for Blue Lagoon Pools. The following table lists the activity time estimates (in days) for Blue Lagoon's swimming pool installation project in Problem 11 (and below). a. What are the critical activities? b. What is the expected time to complete the project? c. Based only on the critical path, what is the estimated probability that the project can be completed in 25 or fewer days?