Question: Critical Path Method Exercises Based on the PMBOK Guide For the following table of information, 1. Draw the network diagram 2. List the network paths

Critical Path Method Exercises Based on the PMBOK Guide

Critical Path Method Exercises Based on the PMBOK

For the following table of information, 1. Draw the network diagram 2. List the network paths 3. Determine the critical path(s) 4. Determine the float for each activity Activity Duration Dependency Float Start O days 5 days Start B 2 days Start C 3 days A,B D 5 days Start E 6 days Start F 4 days D, E G 2 days C, F H 5 days G 7 days G J 3 days H Finish O days 1,J