Question: Critical path method is a project network diagramming approach used to predict total project duration. Which of the following is not true of the critical

Critical path method is a project network diagramming approach used to predict total project duration. Which of the following is not true of the critical path?

a.

Critical path has the least amount of slack

b.

Critical path determines the important activities in the project

c.

Critical path is the longest path through the network diagram

d.

Critical path is the earliest time by which the project can be completed