Question: Critical Path Method Once the sequence of activities has been defined, the project manager asks you these questions: What is the expected duration? What are

Critical Path Method Once the sequence of activities has been defined, the project manager asks you these questions: What is the expected duration? What are the earliest start and finish times? How would the projects expected completion date be affected by different delay

diagram

start - A-B-C-D- End

Start -E-F-D- End

Start -G-H-I-End 3.1 Calculate the duration of the project (in months). Include both the forward pass and backward pass calculations. 3.2 Identify the critical path for this project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!