Question: Critical Path Method Once the sequence of activities has been defined, the project manager asks you these questions: What is the expected duration? What are
Critical Path Method Once the sequence of activities has been defined, the project manager asks you these questions: What is the expected duration? What are the earliest start and finish times? How would the projects expected completion date be affected by different delays in activities?

Calculate the duration of the project (in months). Include both the forward pass and backward pass calculations
Base your answers on the diagram below: 3.1 Calculate the duration of the project (in months). Include both the forward pass and backward pass calculations. (19)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
