Question: D 5 4 C7 B 3 3 2: Using the network above and the additional information bel (a) The crash cost per day (b) Which

D 5 4 C7 B 3 3 2: Using the network above and the

D 5 4 C7 B 3 3 2: Using the network above and the additional information bel (a) The crash cost per day (b) Which activities should be crashed to meet a project de minimum cost? Assume partial crashing is allowed. Crash Tim (days) Crashed Cost (total) $500 325 Normal Time (days) Activity Normal Cost 3 4 $300 B 3 250 550 7 400 D 3 250 5 150