Question: Given the following Activity Crash Time ( days ) Crashed Cost ( total ) Normal Time ( days ) Normal Cost A: Obtain instructor 4
Given the following
Activity Crash Time days Crashed Cost total Normal Time days Normal Cost
A: Obtain instructor
$
$
B: Locate a room
C: Check costs
D: Room open?
E: Schedule class
$
Find the crash cost per day.
Which activities should be crashed to meet a project deadline of days with a minimum cost? Assume partial crashing.
Find the new cost.
Is partial crashing an appropriate assumption in this kind of project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
