Question: Given the following Activity Crash Time ( days ) Crashed Cost ( total ) Normal Time ( days ) Normal Cost A: Obtain instructor 4

Given the following
Activity Crash Time (days) Crashed Cost (total) Normal Time (days) Normal Cost
A: Obtain instructor
4
$800
7
$500
B: Locate a room
2
350
3
200
C: Check costs
4
900
6
500
D: Room open?
1
500
3
200
E: Schedule class
1
550
2
300
$3100
Find the crash cost per day.
Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? Assume partial crashing.
Find the new cost.
Is partial crashing an appropriate assumption in this kind of project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!