Question: D. Activity Crash Cost (Slope) Max Crash Time Normal Time 50 100 4. 60 D. 3. 60 70 Given the table and network above, reduce

D. Activity Crash Cost (Slope) Max Crash Time Normal Time 50 100 4. 60 D. 3. 60 70 Given the table and network above, reduce the project duration the crash point ONE UNIT TIME per pass. Each pass may involve crashing more than one activity. Compute the crash cost. [Stop at the network crash point] Total Cost PASS #2 PASS #1 Total Cost D. B. B. D. Total Cost PASS #3 Total Cost PASS #3 B. D. B. A. Total Cost PASS 6 Total Cost PASS #5 D. B. B