Question: D E 3 C 3 6 Activity Time Earliest Start Earliest Finish Latest Finish Latest Start Slack Activity A 2 0 0 2 0 B

D E 3 C 3 6 Activity Time Earliest Start Earliest

D E 3 C 3 6 Activity Time Earliest Start Earliest Finish Latest Finish Latest Start Slack Activity A 2 0 0 2 0 B 1 2 3 3 4 1 3 2 5 2 5 0 D 7 3 10 4 11 3 5 8 11 3 E F 5 11 5 11 0 G 4 11 15 11 15 0 Using the information shown in the table above, what is the earliest finish time for activity A