Question: begin{tabular}{|c|c|c|c|c|c|c|} hline Activity & Activity Time & Earliest Start & Earliest Finish & Latest Start & Latest Finish & Slack hline A & 2

\begin{tabular}{|c|c|c|c|c|c|c|} \hline Activity
\begin{tabular}{|c|c|c|c|c|c|c|} \hline Activity
\begin{tabular}{|c|c|c|c|c|c|c|} \hline Activity & Activity Time & Earliest Start & Earliest Finish & Latest Start & Latest Finish & Slack \\ \hline A & 2 & 0 & & 0 & 2 & 0 \\ \hline B & 1 & 2 & 3 & 3 & 4 & 1 \\ \hline C & 3 & 2 & 5 & 2 & 5 & 0 \\ \hline D & 7 & 3 & 10 & 4 & 11 & \\ \hline E & 3 & 5 & 8 & & 11 & 3 \\ \hline F & & 5 & 11 & 5 & 11 & 0 \\ \hline \end{tabular} What is the earliest expected time of completion of the whole project? A. Fewer than or equal to 21 days B. Greater than 22 but fewer than or equal to 23 days C. Greater than 23 days D. Greater than 21 but fewer than or equal to 22 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!