Question: D) The estimated time for the critical path is [ ] weeks. E) What is the activity variance along the critical path? F) What is

D) The estimated time for the critical path is [ ] weeks.D) The estimated time for the critical path is [ ] weeks.

E) What is the activity variance along the critical path?

F) What is the probability of completion of the project before week 40?

a) The expected (estimated) time for activity C is weeks. (Round your response to two decimal place b) The variance for activity C is weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is