Question: Daily demand (constant) = 10 Average lead time = 6 days Standard deviation of lead time = LT = 3 85% service level desired .
Daily demand (constant) = 10
Average lead time = 6 days
Standard deviation of lead time = LT = 3
85% service level desired .
Find ROP?
a. 80.72
b. 201
c. 101.72
d. 101