Question: Daily demand (constant) = 10 Average lead time = 6 days Standard deviation of lead time = GLT = 3 98% service level desired Z

Daily demand (constant) = 10 Average lead time = 6 days Standard deviation of lead time = GLT = 3 98% service level desired Z for 98% = 2.055 Find ROP?