Question: Question : Daily demand (constant) = 10 Average lead time = 6 days Standard deviation of lead time = LT = 3 98% service level
Question : Daily demand (constant) = 10 Average lead time = 6 days Standard deviation of lead time = LT = 3 98% service level desired Z for 98% = 2.055 Find ROP?
It would really helpful if someone post the answer with steps and explanation.