Question: Data on small maintenance project is given as below: Depends Normal Activity on Time Cost 6 days $700 4 days 400 C 5 days 650

Data on small maintenance project is given as below: Depends Normal Activity on Time Cost 6 days $700 4 days 400 C 5 days 650 A 8 days 625 10 days 200 B 7 days 500 3 days 600 D, ET 6 days 300 F, G 7 days 350 Crash Time Cost 4 days $800 4 days 400 4 days 700 5 days 700 7 days 350 5 days 700 3 days 600 5 days 400 4 days 425 On completion, the project will give a return of $110/day. Usingtime-cost trade-off method, how much would you like to compress the project for maximizing the return? Show all calculations