Question: Data on the critical path activities based on normal duration are shown below. Identify which activities must be reduced, by how much each is reduced,
Data on the critical path activities based on normal duration are shown below. Identify which activities must be reduced, by how much each is reduced, and the added cost above the normal time cost to reduce the project duration by 3 days from the Normal Time Duration. Your answer must show the new duration of activities you reduce and the total added cost of the reduction.
| Activity | Normal Time days | Normal Duration Cost $ | Shorter Duration Time days | Shorter Duration Cost $ |
| E | 7 | 6000 | 6 | 6600 |
| I | 5 | 9000 | 4 | 9800 |
| N | 6 | 10000 | 4 | 12200 |
| V | 8 | 4000 | 5 | 6700 |
| W | 10 | 13000 | 8 | 15100 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts