Question: QUESTION 4 A certain project has the following activities and budgeted costs, in $1,000: Activity Nov Dec Jan Feb Mar Apr. to Aug. % Completion
QUESTION 4
-
A certain project has the following activities and budgeted costs, in $1,000:
Activity
Nov
Dec
Jan
Feb
Mar
Apr. to Aug.
% Completion till March
A
9
7
--
--
--
--
100
B
--
3
5
7
--
--
80
C
--
--
4
5
8
10
49
D
--
--
--
12
12
24
42
This project is planned for a 10-month duration till August 2020. To evaluate the current situation of this project till the end of March, the earned value, in $1,000, is: