Question: Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D

Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K.
Answer in the Blue Sheet Below
(You must show all formulas, calculations, and "highlight" corrrect Answers)
Activity Optimistic Time Most Likely Time Pessimistic Time Expected duration
A 791410
B 2284
C 8121612
D 35106
E 4686
F 68108
G 2343
H 2284
I 681610
J 46148
K 2253

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!