Question: Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D
Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A D H I J K
Answer in the Blue Sheet Below
You must show all formulas, calculations, and "highlight" corrrect Answers
Activity Optimistic Time Most Likely Time Pessimistic Time Expected duration
A
B
C
D
E
F
G
H
I
J
K