Question: Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D

Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K.
Answer in the Blue Sheet Below
(You must show all formulas, calculations, and "highlight" corrrect Answers)
A. Determine the standard deviation of the critical path. Activity Optimistic Time Most Likely Time Pessimistic Time To determine the standard deviation of the critical path:
A 7914 Calculate the variance for each activity using the formula
B 228 variance =(P-O)^2+
C 81216
D 3510
E 468
F 6810
G 234
H 228
I 6816
J 4614
K 225
B. Determine the probability of completing the project in 38 weeks or less.
C. What is the probability of completing the project in 32 weeks or

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!