Question: Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D
Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A D H I J K
Answer in the Blue Sheet Below
You must show all formulas, calculations, and "highlight" corrrect Answers
A Determine the standard deviation of the critical path. Activity Optimistic Time Most Likely Time Pessimistic Time To determine the standard deviation of the critical path:
A Calculate the variance for each activity using the formula
B variance PO
C
D
E
F
G
H
I
J
K
B Determine the probability of completing the project in weeks or less.
C What is the probability of completing the project in weeks or
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
