Question: PROBLEM # 5 Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is

PROBLEM #5
Data regarding the activities for a project are presented below. The times are in weeks. The
critical path for this project is A - D - H - I - J - K.
Answer in the Blue Sheet Below
(You must show all formulas, calculations, and "highlight" corrrect Answers)
Determine the standard deviation of
the critical path.
B.
Determine the probability of
completing the project in 38 weeks
or less.
What is the probability of
completing the project in 32 weeks
or
 PROBLEM #5 Data regarding the activities for a project are presented