Question: DECS 744 Project Management Use the information contained below to compress one-time units per move using the least cost method. Reduce the schedule until you

DECS 744 Project Management Use the information contained below to compress one-time units per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity was crashed and the adjusted total cost. Note: Choose B instead of C and E (equal costs) because it is usually smarter to crash early rather than late AND one activity instead of two activities. Act Crash Cost Max Crash Normal Normal Slope Time Time Cost A 0 0 2 150 B 100 3 100 N P 50 4 200 D 40 A 200 E 50 3 200 F 0 0 1 150 Total 1000 C Initial 6 project duration 13 A F 3 1x D Total direct cost 1,000 4 3