Question: Define Critical path, Slack time, Resource Leveling and Dummy activity with reference to PERT and CPM. An architect has been awarded a contract to prepare
Define "Critical path", "Slack time", "Resource Leveling" and "Dummy activity" with reference to PERT and CPM. An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
| Job | Description | Predecessor | Expected time in days |
| A | Prepare preliminary sketches | NA | 2 |
| B | Outline specifications | NA | 1 |
| C | Prepare drawings | A | 3 |
| D | Write specifications | A B | 2 |
| E | Run prints | C D | 1 |
| F | Have specifications printed | B D | 3 |
| G | Assemble bid package | E F | 1 |