Question: Define Critical path, Slack time, Resource Levelling and Dummy activity with reference to PERT and CPM . An architect has been awarded a contract to

Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.
An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
Job
Description
Predecessor
Expected time in days
A
Prepare preliminary sketches
NA
2
B
Outline specifications
NA
1
C
Prepare drawings
A
3
D
Write specifications
A B
2
E
Run prints
C D
1
F
Have specifications printed
B D
3
G
Assemble bid package
E F
1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!