Question: Define Critical path, Slack time, Resource Levelling and Dummy activity with reference to PERT and CPM . An architect has been awarded a contract to

Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.
An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
\table[[Job,Description,Predecessor,\table[[Expected time in],[days]]],[A,\table[[Prepare preliminary],[sketches]],NA,2],[B,Outline specifications,NA,1],[C,Prepare drawings,A,3],[D,Write specifications,A B,2],[E,Run prints,C D,1],[F,Have specifications printed,B D,3],[G,Assemble bid package,E F,1]]
 Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!