Question: Dependencies Activity A Duration 2 B 2 4 D 8 E A, F 3 F B 4 G C, D, E 3 H D G

Dependencies Activity A Duration 2 B 2 4 D 8 E A, F 3 F B 4 G C, D, E 3 H D G 2 1 E 7 J G 1. What is the minimum time required to complete the project? 2. What is the Critical Path for this project? 3. What is the Early Start (ES) date for activity E? 4. What is the Late Start (LS) date for activity A? 5. What is the Late Finish (LF) date for activity F