Question: Given the following project WPS, construct the project network using both AOA and AON Techniques. NO. Activity 1 A 2 B 3 4 D 5
Given the following project WPS, construct the project network using both AOA and AON Techniques. NO. Activity 1 A 2 B 3 4 D 5 E 6 F 7 G 8 H Predecessor NON NON NON A A B B B NO. 9 10 11 12 13 14 15 Activity I J K L M N 0 Predecessor DF GK HI J E, L, M, N
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts