Question: , describe the critical path method (CPM). Consider a launch vehicle project, where a software build is on the critical path. If an activity on

, describe the critical path method (CPM). Consider a launch vehicle project, where a software build is on the critical path. If an activity on this critical path, such as a code review, is excepted to be delayed, what is a technique you could use to potentially avoid the delay? What impact on this project's resources (e.g. money, labor hours) would your technique have?