Question: Description The following project has been analyzed: Optimistic Activity Most likely Immediate Pessimistic Time (Hrs.) Predecessors Time (Hrs.) Time (Hrs.) A 4 6 8 B

Description The following project has been
Description The following project has been
Description The following project has been
Description The following project has been analyzed: Optimistic Activity Most likely Immediate Pessimistic Time (Hrs.) Predecessors Time (Hrs.) Time (Hrs.) A 4 6 8 B 1 4.5 07 3 A 3 3 D A 5 6 E 0.5 A 1 1.5 F 3 B, C 4 01 G 1 B, C 1.5 07 ILO E, F 6 7 1 2 E, F 5 00 J 2.5 DH 2.75 4.5 K 3 G1 5 7 a) Construct the PERT network for this problem. b) Identify the critical path and give the estimated project completion time