Question: Use the following project information. Optimistic Time Estimate(weeks) Activity Most Likely Time Estimates (weeks) 3 Pessimistic Time Estimates (weeks) 5 Immediate Predecessor(s) none 2 B

Use the following project information. Optimistic

Use the following project information. Optimistic Time Estimate(weeks) Activity Most Likely Time Estimates (weeks) 3 Pessimistic Time Estimates (weeks) 5 Immediate Predecessor(s) none 2 B 2.4 4 5 5 7 8 A A B,C 3 5 8 OOO 4 13 B,C 7 5 2 9 D E 4 5 6 H 6 6 9 F 4 7 10 J 2 3 3 HI (a) Choose the right network diagram. H A A