Question: Determine: (a) the critical path. (b) the probability that the project will be completed in 22 weeks. Activity A COCO Optimistic 3 6 6 6

Determine:

(a) the critical path.

(b) the probability that the project will be completed in 22 weeks.

Determine: (a) the critical path. (b) the probability that the project will

Activity A COCO Optimistic 3 6 6 6 0.5 2 2 4 1 Most Likely 4 7 9 1 3 5 3 Pessimistic 5 14 12 1.5 10 ENI [1 12 11 B E 6 Finish D Start F F Activity A COCO Optimistic 3 6 6 6 0.5 2 2 4 1 Most Likely 4 7 9 1 3 5 3 Pessimistic 5 14 12 1.5 10 ENI [1 12 11 B E 6 Finish D Start F F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!