Question: table [ [ Activity , Optimistic,Most Likely,Pessimistic ] , [ A , 3 , 4 , 5 ] , [ B , 6 ,

\table[[Activity,Optimistic,Most Likely,Pessimistic],[A,3,4,5],[B,6,7,14],[C,6,9,12],[D,0.5,1,1.5],[E,2,3,10],[F,4,5,12],[G,1,3,11]]
Determine:
(a) the critical path.
(b) the probability that the project will be completed in 22 weeks.
 \table[[Activity,Optimistic,Most Likely,Pessimistic],[A,3,4,5],[B,6,7,14],[C,6,9,12],[D,0.5,1,1.5],[E,2,3,10],[F,4,5,12],[G,1,3,11]] Determine: (a) the critical path. (b) the probability that