Question: Determine (i) the critical path and (ii) project duration for the network given at the end of the assignment. Use the following estimates for Optimistic,

Determine (i) the critical path and (ii) project duration for the network given at the end of the assignment. Use the following estimates for Optimistic, Most Probably, and Pessimistic times for each activity: Activity Immediate Optimistic Most Probable Predecessor Pessimistic A Start 6 B 7 Start C 12 13 A 6 8 D 10 A 10 C 10 E 5 F 6 13 B, D G (Finish) 10 E, F 10 C E G D Finish Start B
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
