Question: Determine the ES, EF, LS, LF, & S for all activities. Compute the Critical Time. Show solutions using graphical PERT diagram (hand-drawn, use ruler) with

Determine the ES, EF, LS, LF, & S for all

Determine the ES, EF, LS, LF, & S for all activities. Compute the Critical Time. Show solutions using graphical PERT diagram (hand-drawn, use ruler) with a correct node configuration to show all data. Indicate the slack time beside the activities. 4 1 8 10 18 5 6 Start 2 10 6 5 8 15 12 7 Finish 9 12 11 4 3 9 7 7