Question: Determine the expected time for each activity. Determine the variance and standard deviation for each activity. Using the critical path ACFHJK, determine the expected completion

- Determine the expected time for each activity.
- Determine the variance and standard deviation for each activity.
- Using the critical path ACFHJK, determine the expected completion time for the project.
- Determine the variance and standard deviation for the project.
- What is the probability of completing the project in less than 40 weeks?
- What is the probability of completion of the project before week 44?
\begin{tabular}{ccccc} \hline & & \multicolumn{3}{c}{ Time Estimates (in weeks) } \\ \cline { 3 - 5 } & Immediate & \multicolumn{3}{c}{ Most } \\ Activity & Predecessor(s) & Optimistic & Likely & Pessimistic \\ \hline A & - & 4 & 8 & 10 \\ B & A & 2 & 8 & 24 \\ C & A & 8 & 12 & 16 \\ D & A & 4 & 6 & 10 \\ E & B & 1 & 2 & 3 \\ F & E, C & 6 & 8 & 20 \\ G & E, C & 2 & 3 & 4 \\ H & F & 2 & 2 & 2 \\ I & F & 6 & 6 & 6 \\ J & D, G, H & 4 & 6 & 12 \\ K & I, J & 2 & 2 & 3 \\ \hline \end{tabular}