Question: Determine the PERT estimate for the project duration based on the table below Duration (days Activity Predecessor a m b A 4 5 6 )

Determine the PERT estimate for the project

Determine the PERT estimate for the project duration based on the table below Duration (days Activity Predecessor a m b A 4 5 6 ) B 1 3 3 5 C 1 2 3 . D 1 2 3 B E 3 6 9 F 1 2 3 | | | T A C, D B G 9 12 15 H 3 5 7 E 1 3 5 7 F, H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!